Saturday, May 10, 2008

PAVING PROJECT UPDATE




THANK YOU, THANK YOU, THANK YOU for your cooperation and patience!! We have completed Week/Phase #1, but Week/Phase #2, when we do the seal coating and striping, is even more important.

Please remember
1. All vehicles (cars, bicycles, motorcycles) ABSOLUTELY MUST BE MOVED for the seal coating and striping work. Call Management with your questions at 480-443-5566. Review your map for days when your vehicles must be moved. Towing will cost you $35 each direction.
2. Be careful driving over the new speed humps. They will not be painted until later during the week.
3. Purdue Avenue and 92nd Street will become ONE-WAY streets. ENTER from Via Linda/92nd Street and EXIT at Purdue/91st Street

WEEK #2 – Seal coating and striping of new asphalt. NO driving, walking, or parking in the closed areas. The seal coating product will cause damage to cars, clothing, carpeting, etc. Regional Paving and Village Two will assume no responsibility. Please read map carefully!

***Tuesday, May 13, 2008 and Wednesday, May 14, 2008.
· Area Closed: 9125 E. Purdue and 9465 N. 92nd Street
· All vehicles must be moved by 6:00 A.M. Tuesday morning and may return Wednesday, the 14th after 5:00 P.M.
· This phase is marked on map WEEK #2,
· You may park your vehicle in 9115 E. Purdue and 9460 N. 92nd Street during this time.

***Thursday May 15…no work will be done because of garbage collection.

***Friday, May 16, 2008 and Saturday, May 17, 2008.
· Area Closed: 9115 E. Purdue and 9460 N. 92nd Street
· All vehicles must be moved by 6:00 A.M. Friday morning and may return Saturday, the 17th after 5:00 P.M.
· This phase is marked on the map WEEK #2,
· You may park your vehicle in 9125 E. Purdue and 9465 N. 92nd Street during this time.

Again, thanks for your cooperation and patience.